How to model Diffractive Optical Element (DOE) with high order
Hi, I am a newbie using Zemax to model DOE. Below is the screenshot. Can you please help on the 2 questions below?
I need to model a DOE with “+/-57 -by- +/-57” orders, however, when I typed in “-57” at “start order”, Zemax automatically filled “-18” at “stop order” and doesn’t support “+57”
can you tell if it’s correct using “binary 1” to model DOE? can you also teach what is each “parameter” mean, e.g. “Clear / Edge / X1Y0 / etc.”
This means you can only trace 40 orders simultaneously. Some of the parameters under the Object Properties can be varied using Multiconfig operand NPRO, but it seems this Start and Stop order setting are not supported by NPRO so you can only trace 40 orders in one system.